Maricopa & Pinal Counties, Arizona
Booth Hills Transmission Project
The Booth Hills Transmission Project (Project) consists of two parallel generation intertie (gen-tie) transmission lines. The Project would connect two proposed solar photovoltaic and energy storage system facilities – Pinyon Solar and Caballero Solar – to the regional electrical grid at the existing Pinal West Substation in Pinal County, Arizona.
WELCOME
This website was created to serve as a place for nearby residents and others interested in the Project to find accurate, up-to-date information, and to provide comments on the Project. We look forward to working with the community to build a successful Project that boosts the local economy and helps Arizona meet its clean energy goals.
Pinyon CEC Approval
Caballero CEC Approval
Project Snapshot
LOCATION
Approximately 8 miles west of the City of Maricopa in unincorporated Maricopa and Pinal counties, Arizona.
View the site map here
PROJECT CAPACITY
The Project would distribute up to a combined 500 megawatts (MW) of solar capacity generated by the proposed Pinyon Solar Project and Caballero Solar Project.
PROJECT COMPONENTS
The Project consists of two components: the Pinyon Gen-tie and Caballero Gen-tie.
PINYON GEN-TIE
The Pinyon Gen-tie component consists of a 345 kV transmission line that would extend 2.8 miles from the proposed Pinyon substation to the Tucson Electric Power (TEP) interconnection at the existing Pinal West Substation.
CABALLERO GEN-TIE
The Caballero Gen-tie component consists of a 500 kV transmission line that would extend 5.3 miles from the Caballero substation to the Salt River Project (SRP) interconnection at the existing Pinal West Substation.
DEVELOPER
The Project is being developed by Avantus (formerly 8minute), a leading solar and energy storage developer with more than a decade of success across the Western United States. 315PC 8me LLC, a subsidiary of Avantus, will be the CEC applicant.
Project Overview
Avantus is developing the Project to transmit renewable energy from the proposed Pinyon Solar Project and Caballero Solar Project to the existing Pinal West Substation. The Project includes the construction of a substation at each proposed solar field and a transmission line corridor containing two generation-interconnect (gen-tie) transmission lines – the Pinyon Gen-tie and Caballero Gen-tie – extending from the new substations to the Pinal West Substation.
The Booth Hills Transmission corridor extends a total of 5.5 miles. The 345 kV Pinyon Gen-tie line extends for 2.8 miles, while the 500 kV Caballero Gen-tie line extends 5.2 miles, with the Pinyon Gen-tie route overlapping almost entirely with the Caballero placement. Colocating the transmission lines within the same corridor limits the Project’s disturbance area and reduces potential visual and environmental impacts.
Gen-tie Transmission Lines
Booth Hills Transmission has two gen-tie transmission lines that would be colocated within the same 200-ft-wide transmission corridor.
Pinyon Gen-tie
345 kV
Located primarily on privately-owned land
2.8 miles long
Caballero Gen-tie
500 kV
Located on BLM and privately-owned land
5.2 miles long
Gen-tie Structures
Structures used for the Booth Hills Transmission Project would be monopoles. Compared to more traditional lattice transmission structures, monopoles offer:
A smaller footprint
Less ground disturbance
Smaller visual impact
Increased wind resistance
Greater structural integrity
Pinyon Gen-tie
The structures supporting the 345 kV line would be 100-140 foot tall monopoles and would typically be spaced between 500 to 1,000 feet apart (center to center), depending on the topographic, hydrologic, and geologic conditions of the underlying lands.
Caballero Gen-tie
The structures supporting the 500 kV line would be 120-180 feet tall and would typically be spaced between 500 to 1,000 feet apart (center to center), depending on the topographic, hydrologic, and geologic conditions of the underlying lands.
This is an example of a monopole structure and may not be representative of what is selected for the Project during final design.
Substations
The two substations proposed for the Project would contain several components such as power transformers, distribution cabinets, revenue metering systems, telecommunications equipment, switch gear, and a control building. The substations would each occupy an area of approximately 0.4 acre within the overall footprint of each respective solar project and would be surrounded by a chain-link fence to limit access and promote safe and secure operation.
Minimizing Environmental Effects
The Project is being designed to minimize potential environmental effects through the following measures:
Colocating the Pinyon gen-tie and Caballero gen-tie within a common transmission corridor to minimize cultural, biological, aesthetic, and future use impacts on the surrounding area
Conducting preconstruction surveys for sensitive resources
Implementing best management practices during construction
Project Virtual Flyover
This simulation of the proposed design shows what the Project is expected to look like once built.
Siting & Environmental Considerations
Please see our FAQs page for additional information and resources.
-
Avantus has a positive track record with local, state, and federal wildlife agencies as well as with environmental organizations. In addition to requiring a Certificate of Environmental Compatibility from the ACC, because Booth Hills Transmission crosses BLM-managed land, the Project is also subject to federal agency review and approval under the National Environmental Policy Act (NEPA). Our past projects have garnered support from respected groups including the Sierra Club, Audubon California, Defenders of Wildlife, and the Natural Resources Defense Council.
We design each project to avoid or minimize potential impacts to threatened or endangered species and ensure proper mitigation measures are provided as appropriate. Booth Hills Transmission is not anticipated to impact any species protected under the Endangered Species Act. -
No, impacts to historic and archaeological features will be avoided. A cultural resources inventory is being conducted within the areas of temporary and permanent disturbance. If historically-relevant features are found, the Project design will be adjusted to avoid impacts to these features.
-
No, Booth Hills Transmission will use minimal water. The biggest use of water over the life of the Project occurs during construction to suppress any dust. After construction, no water use is necessary for the operation and maintenance of the transmission lines.
-
During construction, we expect our crew will generate some noise and add cars/trucks to certain roads, and we will aim to minimize those potential impacts.
As always, we aim to be respectful of our neighbors and aim to keep construction noise to a minimum. All site activity is subject to and will comply with Maricopa County and Pinal County noise ordinances. -
Dust suppression will be used throughout the construction period to control dust and minimize the potential impacts on construction workers and the surrounding community, as mandated by Maricopa County, Pinal County, and Arizona regulations.